Mar 14, 2007

Rebars galore

Tyng reinforcement bars took all day. Inside formwork was started, but they'll need a few more hours tomorrow.

Concrete foundations today (in America) are built using a lot more steel than just a few years ago due to tightening building codes.

Mar 13, 2007

Outer formwork

Outside formboards completed. New foundation will partially sit on the existing concrete patio -- a cost-savings measure -- but the structural bearing is on friction piers. Concrete will be a single pour (monolithic) with the piers. Tomorrow will be steel reinforcement and completion of formwork.

Mar 12, 2007

Drilling pier holes

Today was ground drilling day -- eleven holes, 12" diameter by 8 feet deep each. The top three feet was mostly soft clay, but after that it was what the soils engineer (special inspection was required) called "weathered sandstone." It's basically hardpan. Drilling through it required a special titanium bit and more than half an hour each hole.

Mar 11, 2007

Demo down to studs

I'm doing all interior demolition myself to control the mess as well as potential damage to nearby surfaces. It also allows me to check and fine-tune my designs after uncovering hidden obstructions. For tight designs like mine, project cost is greatly affected by these "micro" logistics.

All but that corner stud will be removed. Looks good so far.

Project: powder room +

The new powder room (half bath consisting of toilet and lavatory) is on the same building permit as the rear addition. Hence, concurrent interior work. Bedroom 4 and the Entry area are integrally affected.